Project

General

Profile

Feature #1460

Marking a Task as Complete should auto-mark subtasks as Complete

Added by Shanna DeSouza over 2 years ago. Updated over 2 years ago.

Status:
Closed
Priority:
Normal
Assignee:
Start date:
03/07/2017
Due date:
% Done:

0%


Description

A feature that was also missing from the old TMS, but if it is possible to mark a top-level task as complete and all the subtasks be marked as complete at the same time, that would be cool.

History

#1 Updated by Shanna DeSouza over 2 years ago

  • Assignee set to Evan Kay

#2 Updated by Evan Kay over 2 years ago

I agree. If I then mark a completed parent task as incomplete, should that also change the subtasks to incomplete? I'm thinking it shouldn't.

#3 Updated by Shanna DeSouza over 2 years ago

Evan Kay wrote:

I agree. If I then mark a completed parent task as incomplete, should that also change the subtasks to incomplete? I'm thinking it shouldn't.

Would it be possible to temporarily remember which subtasks were marked as complete when the parent task is marked as complete? Scenario is that a parent task is accidentally marked as complete and some of its children were already marked as complete but some not and then the parent is unmarked as complete and the children that were recently marked as complete are also unmarked complete. This scenario seems complicated, so an alternative is to make it a little more difficult to accidentally mark a task as complete such as adding a 2nd step when marking the task as complete where you verify you want to mark the task as complete and at that time you can check a box to choose to also mark the subtasks as complete.

#4 Updated by Evan Kay over 2 years ago

  • Status changed from New to Implemented

#5 Updated by Evan Kay over 2 years ago

  • Status changed from Implemented to Closed

Also available in: Atom PDF